April Project Plan
This may be much less organised than it looks, but here is the detailed project plan for Rightsite.Asia, my new online marketplace for industrial property. Will try to update this from time to time as stuff goes off the rails
|
Name
|
Duration | Start_Date | Finish_Date | Predecessors |
|---|---|---|---|---|
|
Establish offshore co
|
20 days | Wed 11/21/07 | Tue 12/18/07 | |
|
Hire admin team
|
1 day | Wed 12/19/07 | Wed 12/19/07 | 1 |
|
Get certificate of incumbency
|
7 days | Wed 12/19/07 | Thu 12/27/07 | 1 |
|
Open bank account
|
7 days | Fri 12/28/07 | Mon 1/7/08 | 3 |
|
Activate bank account
|
7 days | Tue 1/8/08 | Wed 1/16/08 | 4 |
|
Receive bank recommendation letter
|
7 days | Thu 1/17/08 | Fri 1/25/08 | 5 |
|
Hire consultant for WOFE
|
1 day | Wed 12/19/07 | Wed 12/19/07 | 1 |
|
Gather WOFE documents
|
2 days | Thu 12/20/07 | Fri 12/21/07 | 7 |
|
Establish WOFE
|
90 days | Mon 1/28/08 | Fri 6/13/08 | 6,8 |
|
Define customers
|
1 day | Wed 12/19/07 | Wed 12/19/07 | 1 |
|
Define needs of customers
|
5 days | Thu 12/20/07 | Wed 12/26/07 | 10 |
|
List website requirements
|
5 days | Thu 12/27/07 | Wed 1/2/08 | 11 |
|
Development of website brief
|
4 days | Thu 1/3/08 | Tue 1/8/08 | 12 |
|
Development of page function briefs
|
4 days | Wed 1/9/08 | Mon 1/14/08 | 13 |
|
Development of page fields
|
5 days | Tue 1/15/08 | Mon 1/21/08 | 14 |
|
Search for web dev vendor
|
10 days | Tue 1/22/08 | Mon 2/18/08 | 15 |
|
Request development proposals
|
1 day | Tue 2/19/08 | Tue 2/19/08 | 16 |
|
Receive development proposals
|
12 days | Wed 2/20/08 | Thu 3/6/08 | 17 |
|
Review development proposals
|
10 days | Fri 3/7/08 | Thu 3/20/08 | 18 |
|
Negotiate website building contract
|
10 days | Fri 3/21/08 | Thu 4/3/08 | 19 |
|
Develop website requirements doc
|
20 days | Fri 4/4/08 | Thu 5/1/08 | 20 |
|
Site Map
|
10 days | Fri 4/4/08 | Thu 4/17/08 | 20 |
|
Site Visual Design Guide
|
30 days | Fri 4/4/08 | Thu 5/15/08 | 20 |
|
Site High level design
|
30 days | Fri 4/4/08 | Thu 5/15/08 | 20 |
|
Deploy Beta site
|
65 days | Fri 4/4/08 | Thu 7/3/08 | 20 |
|
Start Site UAT
|
75 days | Fri 4/4/08 | Thu 7/17/08 | 20 |
|
Site Launch
|
0 days | Thu 7/17/08 | Thu 7/17/08 | 26 |
|
MC returns from CNY
|
0 days | Mon 2/18/08 | Mon 2/18/08 | |
|
VV returns from CNY
|
1 day | Thu 2/28/08 | Thu 2/28/08 | |
|
Create IZ Module brief
|
3 days | Fri 2/29/08 | Tue 3/4/08 | 29 |
|
Create IZ module
|
15 days | Wed 3/5/08 | Tue 3/25/08 | 30 |
|
Recruit data entry interns
|
20 days | Wed 3/26/08 | Tue 4/22/08 | 31 |
|
Start data entry interns
|
1 day | Wed 4/23/08 | Wed 4/23/08 | 32 |
|
Web db content entry
|
30 days | Thu 4/24/08 | Wed 6/4/08 | 33 |
|
Web db content checking
|
7 days | Thu 6/5/08 | Fri 6/13/08 | 34 |
|
Web db content corrections
|
7 days | Mon 6/16/08 | Tue 6/24/08 | 35 |
|
Static content planning
|
2 days | Fri 5/16/08 | Mon 5/19/08 | 24 |
|
Static content writing
|
3 days | Tue 5/20/08 | Thu 5/22/08 | 37 |
|
Static content editing
|
2 days | Fri 5/23/08 | Mon 5/26/08 | 38 |
|
Develop marketing plan
|
25 days | Thu 12/27/07 | Wed 1/30/08 | 11 |
|
Recruit marketing team
|
60 days | Fri 4/18/08 | Thu 7/10/08 | 40,22 |
|
List newsletter requirements
|
1 day | Fri 7/11/08 | Fri 7/11/08 | 41 |
|
Newsletter design
|
1 day | Mon 7/14/08 | Mon 7/14/08 | 42 |
|
Newsletter construction
|
1 day | Tue 7/15/08 | Tue 7/15/08 | 43 |
|
Develop mailing list requirements
|
1 day | Mon 7/14/08 | Mon 7/14/08 | 42 |
|
Dist db design
|
1 day | Tue 7/15/08 | Tue 7/15/08 | 45 |
|
Dist db construction
|
1 day | Wed 7/16/08 | Wed 7/16/08 | 46 |
|
Dist db data import and cleanup
|
1 day | Thu 7/17/08 | Thu 7/17/08 | 47 |
|
Send first newsletters
|
1 day | Fri 7/18/08 | Fri 7/18/08 | 48,44 |
|
Find office
|
20 days | Tue 4/1/08 | Mon 4/28/08 | |
|
Find build-out vendor
|
15 days | Tue 4/29/08 | Mon 5/19/08 | 50 |
|
Build-out office
|
20 days | Tue 5/20/08 | Mon 6/16/08 | 51 |
|
Hire Sales director
|
60 days | Fri 5/16/08 | Thu 8/7/08 | 24 |
|
Hire Sales Team
|
60 days | Fri 5/16/08 | Thu 8/7/08 | 24 |