Project Plan 2008-07-08
| ID |
Task_Name
|
Duration | Start_Date | Finish_Date | Predecessors | Resource_Names |
|---|---|---|---|---|---|---|
| 1 |
Establish offshore co
|
20 days | Wed 11/21/07 | Tue 12/18/07 | ||
| 2 |
Hire admin team
|
1 day | Wed 12/19/07 | Wed 12/19/07 | 1 | |
| 3 |
Get certificate of incumbency
|
7 days | Wed 12/19/07 | Thu 12/27/07 | 1 | |
| 4 |
Open offshore bank account
|
7 days | Fri 12/28/07 | Mon 1/7/08 | 3 | |
| 5 |
Activate bank account
|
7 days | Tue 1/8/08 | Wed 1/16/08 | 4 | |
| 6 |
Receive bank recommendation letter
|
7 days | Thu 1/17/08 | Fri 1/25/08 | 5 | |
| 7 |
Hire consultant for WOFE
|
1 day | Wed 12/19/07 | Wed 12/19/07 | 1 | |
| 8 |
Gather WOFE documents
|
2 days | Thu 12/20/07 | Fri 12/21/07 | 7 | |
| 9 |
Establish WOFE
|
90 days | Mon 1/28/08 | Fri 6/13/08 | 6,8 | |
| 10 |
Define customers
|
1 day | Wed 12/19/07 | Wed 12/19/07 | 1 | |
| 11 |
Define needs of customers
|
5 days | Thu 12/20/07 | Wed 12/26/07 | 10 | |
| 12 |
List website requirements
|
5 days | Thu 12/27/07 | Wed 1/2/08 | 11 | |
| 13 |
Development of website brief
|
4 days | Thu 1/3/08 | Tue 1/8/08 | 12 | |
| 14 |
Development of page function briefs
|
4 days | Wed 1/9/08 | Mon 1/14/08 | 13 | |
| 15 |
Development of page fields
|
5 days | Tue 1/15/08 | Mon 1/21/08 | 14 | |
| 16 |
Search for web dev vendor
|
10 days | Tue 1/22/08 | Mon 2/18/08 | 15 | |
| 17 |
Request development proposals
|
1 day | Tue 2/19/08 | Tue 2/19/08 | 16 | |
| 18 |
Receive development proposals
|
12 days | Wed 2/20/08 | Thu 3/6/08 | 17 | |
| 19 |
Review development proposals
|
10 days | Fri 3/7/08 | Thu 3/20/08 | 18 | |
| 20 |
Negotiate website building contract
|
10 days | Fri 3/21/08 | Thu 4/3/08 | 19 | |
| 21 |
Develop website requirements doc
|
35 days | Fri 4/4/08 | Thu 5/22/08 | 20 | |
| 22 |
Site Map
|
10 days | Fri 4/4/08 | Thu 4/17/08 | 20 | |
| 23 |
Site Visual Design Guide
|
30 days | Fri 4/4/08 | Thu 5/15/08 | 20 | |
| 24 |
Site High level design
|
30 days | Fri 4/4/08 | Thu 5/15/08 | 20 | |
| 25 |
Page Layouts
|
25 days | Fri 5/16/08 | Thu 6/19/08 | 24 | |
| 26 |
Technical Development Plan
|
15 days | Fri 5/23/08 | Thu 6/12/08 | 21 | |
| 27 |
Test Functional Units
|
25 days | Fri 6/13/08 | Thu 7/17/08 | 21,26 | |
| 28 |
Deploy Beta site
|
10 days | Fri 7/18/08 | Thu 7/31/08 | 20,27 | |
| 29 |
Start Site UAT
|
10 days | Fri 8/1/08 | Thu 8/14/08 | 28 | |
| 30 |
Launch Phase I
|
0 days | Thu 8/14/08 | Thu 8/14/08 | 29 | |
| 31 |
Gather Requirements Phase II
|
25 days | Fri 8/15/08 | Thu 9/18/08 | 30 | |
| 32 |
Requirements Documents Phase II
|
25 days | Fri 9/19/08 | Thu 10/23/08 | 31 | |
| 33 |
Build Phase II
|
25 days? | Fri 10/24/08 | Thu 11/27/08 | 32 | |
| 34 |
Test Phase II
|
10 days | Fri 11/28/08 | Thu 12/11/08 | 33 | |
| 35 |
Launch Phase II
|
1 day? | Fri 12/12/08 | Fri 12/12/08 | 34 | |
| 36 |
MC returns from CNY
|
0 days | Mon 2/18/08 | Mon 2/18/08 | ||
| 37 |
VV returns from CNY
|
1 day | Thu 2/28/08 | Thu 2/28/08 | ||
| 38 |
Create IZ Module brief
|
3 days | Fri 2/29/08 | Tue 3/4/08 | 37 | |
| 39 |
Create IZ module
|
15 days | Wed 3/5/08 | Tue 3/25/08 | 38 | |
| 40 |
Recruit data entry interns
|
20 days | Wed 3/26/08 | Tue 4/22/08 | 39 | |
| 41 |
Start data entry interns
|
1 day | Wed 4/23/08 | Wed 4/23/08 | 40 | |
| 42 |
Web db content entry
|
30 days | Thu 4/24/08 | Wed 6/4/08 | 41 | |
| 43 |
Web db content checking
|
7 days | Thu 6/5/08 | Fri 6/13/08 | 42 | |
| 44 |
Web db content corrections
|
7 days | Mon 6/16/08 | Tue 6/24/08 | 43 | |
| 45 |
Static content planning
|
2 days | Fri 5/16/08 | Mon 5/19/08 | 24 | |
| 46 |
Static content writing
|
3 days | Tue 5/20/08 | Thu 5/22/08 | 45 | |
| 47 |
Static content editing
|
2 days | Fri 5/23/08 | Mon 5/26/08 | 46 | |
| 48 |
Develop marketing plan
|
25 days | Thu 12/27/07 | Wed 1/30/08 | 11 | |
| 49 |
Recruit marketing team
|
60 days | Fri 4/18/08 | Thu 7/10/08 | 48,22 | |
| 50 |
List newsletter requirements
|
1 day | Fri 7/11/08 | Fri 7/11/08 | 49 | |
| 51 |
Newsletter design
|
14 days | Mon 7/14/08 | Thu 7/31/08 | 50 | |
| 52 |
Newsletter construction
|
1 day | Fri 8/1/08 | Fri 8/1/08 | 51 | |
| 53 |
Develop mailing list requirements
|
1 day | Mon 7/14/08 | Mon 7/14/08 | 50 | |
| 54 |
Dist db design
|
1 day | Tue 7/15/08 | Tue 7/15/08 | 53 | |
| 55 |
Dist db construction
|
1 day | Wed 7/16/08 | Wed 7/16/08 | 54 | |
| 56 |
Dist db data import and cleanup
|
1 day | Thu 7/17/08 | Thu 7/17/08 | 55 | |
| 57 |
Begin Marketing Campaign
|
1 day? | Fri 8/15/08 | Fri 8/15/08 | 30 | |
| 58 |
Send first newsletters
|
1 day | Mon 8/18/08 | Mon 8/18/08 | 52,57 | |
| 59 |
Find office
|
20 days | Mon 12/15/08 | Fri 1/9/09 | 35 | |
| 60 |
Find build-out vendor
|
15 days | Mon 1/12/09 | Fri 2/6/09 | 59 | |
| 61 |
Build-out office
|
20 days | Mon 2/9/09 | Fri 3/6/09 | 60 | |
| 62 |
Hire Sales director
|
60 days | Mon 12/15/08 | Fri 3/13/09 | 24,30,35 | |
| 63 |
Hire Sales Team
|
60 days | Mon 3/16/09 | Fri 6/5/09 |