Project Plan 2008-07-08

ID
Task_Name
Duration Start_Date Finish_Date Predecessors Resource_Names
1
Establish offshore co
20 days Wed 11/21/07 Tue 12/18/07
2
Hire admin team
1 day Wed 12/19/07 Wed 12/19/07 1
3
Get certificate of incumbency
7 days Wed 12/19/07 Thu 12/27/07 1
4
Open offshore bank account
7 days Fri 12/28/07 Mon 1/7/08 3
5
Activate bank account
7 days Tue 1/8/08 Wed 1/16/08 4
6
Receive bank recommendation letter
7 days Thu 1/17/08 Fri 1/25/08 5
7
Hire consultant for WOFE
1 day Wed 12/19/07 Wed 12/19/07 1
8
Gather WOFE documents
2 days Thu 12/20/07 Fri 12/21/07 7
9
Establish WOFE
90 days Mon 1/28/08 Fri 6/13/08 6,8
10
Define customers
1 day Wed 12/19/07 Wed 12/19/07 1
11
Define needs of customers
5 days Thu 12/20/07 Wed 12/26/07 10
12
List website requirements
5 days Thu 12/27/07 Wed 1/2/08 11
13
Development of website brief
4 days Thu 1/3/08 Tue 1/8/08 12
14
Development of page function briefs
4 days Wed 1/9/08 Mon 1/14/08 13
15
Development of page fields
5 days Tue 1/15/08 Mon 1/21/08 14
16
Search for web dev vendor
10 days Tue 1/22/08 Mon 2/18/08 15
17
Request development proposals
1 day Tue 2/19/08 Tue 2/19/08 16
18
Receive development proposals
12 days Wed 2/20/08 Thu 3/6/08 17
19
Review development proposals
10 days Fri 3/7/08 Thu 3/20/08 18
20
Negotiate website building contract
10 days Fri 3/21/08 Thu 4/3/08 19
21
Develop website requirements doc
35 days Fri 4/4/08 Thu 5/22/08 20
22
Site Map
10 days Fri 4/4/08 Thu 4/17/08 20
23
Site Visual Design Guide
30 days Fri 4/4/08 Thu 5/15/08 20
24
Site High level design
30 days Fri 4/4/08 Thu 5/15/08 20
25
Page Layouts
25 days Fri 5/16/08 Thu 6/19/08 24
26
Technical Development Plan
15 days Fri 5/23/08 Thu 6/12/08 21
27
Test Functional Units
25 days Fri 6/13/08 Thu 7/17/08 21,26
28
Deploy Beta site
10 days Fri 7/18/08 Thu 7/31/08 20,27
29
Start Site UAT
10 days Fri 8/1/08 Thu 8/14/08 28
30
Launch Phase I
0 days Thu 8/14/08 Thu 8/14/08 29
31
Gather Requirements Phase II
25 days Fri 8/15/08 Thu 9/18/08 30
32
Requirements Documents Phase II
25 days Fri 9/19/08 Thu 10/23/08 31
33
Build Phase II
25 days? Fri 10/24/08 Thu 11/27/08 32
34
Test Phase II
10 days Fri 11/28/08 Thu 12/11/08 33
35
Launch Phase II
1 day? Fri 12/12/08 Fri 12/12/08 34
36
MC returns from CNY
0 days Mon 2/18/08 Mon 2/18/08
37
VV returns from CNY
1 day Thu 2/28/08 Thu 2/28/08
38
Create IZ Module brief
3 days Fri 2/29/08 Tue 3/4/08 37
39
Create IZ module
15 days Wed 3/5/08 Tue 3/25/08 38
40
Recruit data entry interns
20 days Wed 3/26/08 Tue 4/22/08 39
41
Start data entry interns
1 day Wed 4/23/08 Wed 4/23/08 40
42
Web db content entry
30 days Thu 4/24/08 Wed 6/4/08 41
43
Web db content checking
7 days Thu 6/5/08 Fri 6/13/08 42
44
Web db content corrections
7 days Mon 6/16/08 Tue 6/24/08 43
45
Static content planning
2 days Fri 5/16/08 Mon 5/19/08 24
46
Static content writing
3 days Tue 5/20/08 Thu 5/22/08 45
47
Static content editing
2 days Fri 5/23/08 Mon 5/26/08 46
48
Develop marketing plan
25 days Thu 12/27/07 Wed 1/30/08 11
49
Recruit marketing team
60 days Fri 4/18/08 Thu 7/10/08 48,22
50
List newsletter requirements
1 day Fri 7/11/08 Fri 7/11/08 49
51
Newsletter design
14 days Mon 7/14/08 Thu 7/31/08 50
52
Newsletter construction
1 day Fri 8/1/08 Fri 8/1/08 51
53
Develop mailing list requirements
1 day Mon 7/14/08 Mon 7/14/08 50
54
Dist db design
1 day Tue 7/15/08 Tue 7/15/08 53
55
Dist db construction
1 day Wed 7/16/08 Wed 7/16/08 54
56
Dist db data import and cleanup
1 day Thu 7/17/08 Thu 7/17/08 55
57
Begin Marketing Campaign
1 day? Fri 8/15/08 Fri 8/15/08 30
58
Send first newsletters
1 day Mon 8/18/08 Mon 8/18/08 52,57
59
Find office
20 days Mon 12/15/08 Fri 1/9/09 35
60
Find build-out vendor
15 days Mon 1/12/09 Fri 2/6/09 59
61
Build-out office
20 days Mon 2/9/09 Fri 3/6/09 60
62
Hire Sales director
60 days Mon 12/15/08 Fri 3/13/09 24,30,35
63
Hire Sales Team
60 days Mon 3/16/09 Fri 6/5/09